New Welfare Block for Cosworth Engineering

Worcester

Project duration: 10 Weeks

Completed: 2009

3000 Sq ft

Project Included:            

  • Enclosure of Mezzanine Floor
  • Suspended Ceilings with specialist lighting
  • Air Conditioning & Extract Systems
  • Electrical & Mechanical Works
  • Full WC Area re-fit
  • Floor Coverings & Redecoration

 

Project Description:

  • Kube Office Interiors won the project to create the new Welfare Facilities at Cosworths offices & manufacturing plant in Worcester.
  • The project included full Mechanical & Electrical design, including installation of specialist extraction systems, air conditioning, shower facilities, wc areas & changing facilities.
  • Altro safety flooring was utilised in all areas, with compound screed materials 'laid to fall' forming waste water routes underneath the flooring material.
  • The installation was carried out directly opposite the main blast furnaces, all materials selected had to be able to cope with severe temperature swings in the vicinity.