Case studyCosworth Engineering
New Welfare Block for Cosworth Engineering
Worcester
Project duration: 10 Weeks
Completed: 2009
3000 Sq ft
Project Included:
- Enclosure of Mezzanine Floor
- Suspended Ceilings with specialist lighting
- Air Conditioning & Extract Systems
- Electrical & Mechanical Works
- Full WC Area re-fit
- Floor Coverings & Redecoration
Project Description:
- Kube Office Interiors won the project to create the new Welfare Facilities at Cosworths offices & manufacturing plant in Worcester.
- The project included full Mechanical & Electrical design, including installation of specialist extraction systems, air conditioning, shower facilities, wc areas & changing facilities.
- Altro safety flooring was utilised in all areas, with compound screed materials 'laid to fall' forming waste water routes underneath the flooring material.
- The installation was carried out directly opposite the main blast furnaces, all materials selected had to be able to cope with severe temperature swings in the vicinity.